Creston Waterworks Board Tuesday approved a payment of $84,959 toward the North Maple Street water main work, a project that is progressing well according to General Manager Steve Guthrie.
“It’s a good contractor,” he said.
Started July 22, replacement of the water infrastructure will be done in the 100, 200 and 300 blocks of North Maple Street. Some pieces date back to the late 1800s.
During this time, customers can expect disruptions in their water service. Creston Water will notify customers 24 hours ahead of time. However this may not be possible due to complications with construction. Work is progressing on the west side of the street to the intersection with Howard. Work will then shift to the center of North Maple.
As part of this project, the Creston Waterworks will be replacing all or part of each service line at no cost to the customer. If the service line is lead or galvanized steel, Creston will replace the service line to the water meter and access to business/residence will be needed. If the service line is copper, the line will be replaced up to and including the outside shutoff. Any re-surfacing (sidewalks, curbs, etc.) will be replaced in as good or better condition than prior to construction
This project will also limit parking and restrict traffic, so expect delays. Foot traffic will still be an option for accessing businesses in the area. The project is expected to continue into late September.
In other water news...
The water level at Twelve Mile Lake is at capacity. Since the spring rains, the water level has been more than level.
Guthrie said the water treatment system is still being researched for the shortage in water quantity production. Noticed last summer, the desired produced amount by the minute was not being met. The lesser quantity of water produced was never a threat to customers. Southern Iowa Rural Water Association has used its own plant beginning this year rather than Creston Water.
Radio meter read installation is expected to be finished in late October. Radio meters allow for faster meter reading.
Guthrie said he is still waiting for the funding process from the federal government to replace lead pipes.